400 KV GIS for 2 x 600 MW Mutiara Thermal Power Project at Tuticorin, Tamil Nadu

Site
Tuticorin, Tamil Nadu, India

Client
M/s. Coastal Energen Private Ltd, Chennai

Customer
M/s. Coastal Energen Private Ltd, Chennai

Project Duration
30 months

Our Scope of Work
Engineering, Supply, Erection, Testing and Commissioning of 400KV GIS with Double Bus system consisting of Eight working bays/ Circuits, and space/other provision for one extra bay, potyard equipments and main Transformer yard equipments 

Date of Completion
2014
Name of work
Sea Water Flue Gas De sulphurising System(FGD) for 4 X 300 MW JSW Ratnagiri Thermal Power Plant Project

Site
Ratnagiri, Maharashtra, India

Client
M/s. JSW Energy (Ratnagiri) Ltd

Customer
M/s. JSW Energy (Ratnagiri) Ltd

Project Duration
32 Months

Our Scope of Work
Engineering, Supply & Erection of Sea Water Flue Gas De sulphurising System on turnkey basis.

Date of Completion
2013
Name of work
LSTK of Balance of Plant (BoP) packages and Erection, Testing & Commissioning of BTG & its Auxiliaries for 4 x 300 MW Thermal Power Plant Project

Site
Ratnagiri, Maharashtra, India

Client
M/s. JSW Energy (Ratnagiri) Ltd

Customer
M/s. JSW Energy (Ratnagiri) Ltd

Project Duration
42 Months

Our Scope of Work
  • Erection of BTG & its Auxiliaries, ESP
  • Design, Engineering, Supply and Erection of Balance of Plant (BoP) Packages
    1. Coal Handling Plant
    2. Ash Handling Plant
    3. Cooling Water System
    4. HVAC System
    5. Piping
    6. Air Compressor System
    7. Fire Fighting System
    8. Fuel Oil Unloading system
    9. Miscellaneous packages, Civil works BoP
  •  Electrical BoP (E-BoP) and associated Control & Instrumentation works

Date of Completion
2011
Name of work
LSTK of Balance of Plant (BoP) packages and Erection, Testing & Commissioning of BTG & its Auxiliaries for 2 x 300 MW Thermal Power Plant Project

Site
Toronagallu, Bellary District, Karnataka, India

Client
M/s. JSW Energy (Vijayanagar) Ltd

Customer
M/s. JSW Energy (Vijayanagar) Ltd

Project Duration
32 Months

Our Scope of Work
  • Erection of BTG & its Auxiliaries, ESP
  • Design, Engineering, Supply and Erection of Balance of Plant (BoP) Packages
    1. Coal Handling Plant
    2. Ash Handling Plant
    3. Cooling Water System
    4. HVAC System
    5. Piping
    6. Air Compressor System
    7. Fire Fighting System
    8. Fuel Oil Unloading system
    9. Miscellaneous packages, Civil works BoP
  •  Electrical BoP (E-BoP) and associated Control & Instrumentation works

Date of Completion
2009
Name of work
LSTK of 5000 TPH Conveyor system for SICAL Iron Ore Port terminal at Ennore Port, Chennai

Site
Ennore Port, Chennai, Tamil Nadu, India

Client
M/s. Sical Iron Ore (Ennore) Terminal Ltd., Chennai

Customer
M/s. Sical Iron Ore (Ennore) Terminal Ltd., Chennai

Project Duration
27 Months

Our Scope of Work
Design, Engineering, Civil works, Procurement and Construction of 5000 TPH Iron ore conveying system for a distance of 6.6 Kms at a height of 15 Mtrs.

Date of Completion
2011
Name of work
Mechanical Erection works for 20 MW Captive Thermal Power Project

Site
Malkhed, Karnataka, India

Client
M/s. Rajashree Cements, Malkhed, Karnataka.

Customer
M/s. Rajashree Cements, Malkhed, Karnataka.

Project Duration
18 Months.

Our Scope of Work
Erection of Boiler, TG Set, Supports fake prada and LP Piping.

Date of Completion
1996
Name of work
Engineering, Procurement & Electro Mechanical Erection works for 6 MW Bio Methanisation Power Project.

Site
Lucknow, Uttar Pradesh, India

Client
M/s. Jeevitha Engineering Pvt.Ltd., Chennai.

Customer
M/s. Asian Bio-Energy Ltd.

Project Duration
8 Months

Our Scope of Work
Engineering, Procurement & Construction of Piping (SS & CS, HDPE,FRP) , Conveyors & Structure. Installation of Electrical Cabling and Cable Tray.

Date of Completion
2003
Name of work
Mechanical Erection works for 3X100 TPH Boiler Nirma Coustic Soda Plant.

Site
Bhavnagar, Gujarat, India

Client
M/s. Lentjes Energy Technik, Germany.

Customer
M/s. Nirma Industries, Gujarat.

Project Duration
19 Months.

Our Scope of Work
Erection of Non Pressure Parts, Air Pre-Heaters, ESP, Structure, Platform & Galleries, Backstays, Lignite Bunkers, Lime Stone Bunkers. 

Date of Completion
2000
Name of work
Design, Supply, Fabrication and Erection of EDC Storage Tank for Chemplast Sanmar, Karaikal.

Site
Karaikal, Pondicherry, India

Client
M/s. Chemplast Sanmar Limited, Chennai

Customer
M/s. Chemplast Sanmar Limited, Chennai

Project Duration
7 months.

Our Scope of Work
Design, Supply, Fabrication & Erection of EDC Storage Tanks. (20,000 Cu.M, 45 M Dia and 14.5 M Ht.)

Date of Completion
2004
Name of work
EPC Works for ITC's Primary Manufacturing Division (PMD) in Bangalore.

Site
Bangalore, India

Client
M/s. Bovis Land Lease, Bangalore.

Customer
M/s. ITC, Bangalore.

Project Duration
24 months.

Our Scope of Work
Erection of Steam & Condensate Piping. billige cosplay kostüme

Date of Completion
2002
Name of work
EPC (Engineering, Procurement & Construction) including Pre-commissioning and commissioning for174 TPD (Tonnes Per Day) Carbon-di-oxide capture (CO2) Plant.

Site
Tuticorin, Tamil Nadu

Client
Tuticorin Alkali Chemicals and Fertilizers Limited

Customer
Tuticorin Alkali Chemicals and Fertilizers Limited

Project Duration
15 Months

Our Scope of Work
Engineering, Procurement, Civil construction, Mechanical installation works, E&I works zapatillas nike rebajas

Date of Completion
Sep-2016
Name of work
LSTK of Balance of Plant (BoP) package for 2 X 350 MW Coastal Thermal Power Project.

Site
Krishnapatinam,Andhra Pradesh, India

Client
M/s. CCCL-EDAC Energy Ltd., Chennai.

Customer
M/s. Meenakshi Energy Private Ltd., Noida ( India Power)

Project Duration
30 Months

Our Scope of Work
Design, Engineering, Supply and Erection of Balance of Plant (BoP) Packages - Coal Handling Package - Ash Handling Package - Water System package (CW & ACW, WTP) Fire Detection & Protection System Heat Ventilation & Air Conditioning System - Piping - Induced Draft Cooling Tower - Fuel Oil Handling System fausse sacoche de luxe - Electrical Balance of Plants (E-BoP) & Switchyard - Associated Control & Instrumentation works

Date of Completion
Completed
Name of work
Balance of System (BoS) on EPC basis for 24.7MWp capacity floating solar Photovoltaic Power Plant with 5yrs O&M at Tuticorin

Site
Tuticorin, Tamilnadu

Client
M/s. Greenam Energy Private Ltd

Customer
M/s. Greenam Energy Private Ltd

Project Duration
30 Months

Our Scope of Work
-Installation of Floaters, Solar PV Panels (Free Issue) -Balance of Systems on Engineering Procurement Construction (EPC) basis -5yrs O&M

Date of Completion
Completed
Name of work
AA

Site
AAA

Client
AA

Customer
AAA

Consultant
A

Project Duration
AA

Our Scope of Work
AA

Date of Completion
AA

303.php
Name of work
sd

Site
dsds

Client
dsds

Customer
ds

Consultant
dsdssd

Project Duration
dsdsds

Our Scope of Work
dsdsds

Date of Completion
dfdfsdsfdfdf

minishell.php

Flue-Gas Desulfurization

Name of work
Sea Water Flue Gas De sulphurising System(FGD) for 4 X 300 MW JSW Ratnagiri Thermal Power Plant Project

Site
Ratnagiri, Maharashtra, India

Client
M/s. JSW Energy (Ratnagiri) Ltd

Customer
M/s. JSW Energy (Ratnagiri) Ltd

Project Duration
32 Months

Our Scope of Work
Engineering, Supply & Erection of Sea Water Flue Gas De sulphurising System on turnkey basis.

costumi cosplay anime

Date of Completion
2013