Power
MECHANICAL PROJECTS
Name of work
Mechanical Erection,Testing and Commissioning of Boiler & its auxiliaries of 1 x 270MW (Unit #4), for 4 x 270 MW Bhadradri Thermal Power Project at Manuguru. Site Manuguru, Telangana
Site
Manuguru, Telangana
Client
M/s. BHEL-PSWR
Customer
M/s.TS Genco
Project Duration
17 Months
Our Scope of Work
Boiler
and its auxiliaries
Date of Completion
Ongoing
Name of work
Mechanical Erection and Installation of Unit #2, 800MW Boiler and BOP (Package B&D ) for 2x800 MW Godda Thermal Power Projects
Site
Godda, Jharkhand
Client
M/s.HTG Engineering Private Limited, China
Customer
M/s. Adani Jharkhand Power Ltd
Project Duration
23 months
Date of Completion
Ongoing
Name of work
Mechanical Erection works of ESP & its auxiliaries for UNIT#1 800MW, Flue Gas Desulphurization System (FGD) UNIT#1 and Common system of FGD SYSTEM for 3 x 800MW Thermal Power Plant of PVUNL Project, Patratu, Dist.: Ramgarh, State: Jharkhand
Site
Patratu, Dist.: Ramgarh, State: Jharkhand
Client
M/s. BHEL-PSWR, Nagpur
Customer
M/s. Patratu Vidyut Utpadan Nigam Limited
Project Duration
24 months
Our Scope of Work
ESP & its Auxiliaries (Unit#1 800MW );
Unit#1 800MW FGD systems (Absorber, Tanks, Rotary Machines, Piping, Insulation, Painting)
Common systems of FGD for 3x800MW
Date of Completion
Ongoing
Name of work
Mechanical Erection works of Power Cycle Piping for 1 x 660 MW Thermal Power Project at Panki, Dist: Kanpur, Uttar Pradesh
Site
Panki, Uttar Pradesh
Client
M/s. BHEL-PSNR, Nagpur
Customer
M/s. UTTAR PRADESH RAJYA VIDYUT UTPADAN NIGAM LIMITED
Project Duration
22 months
Our Scope of Work
Power
Cycle Piping (P91) Associated Piping (P11/12/22 ; SS, CS, Valves), Tanks & Equipment works Insulation, Painting, etc., |
Date of Completion
Ongoing
Name of work
Mechanical Erection works of U#1, 660MW Boiler & its Auxiliaries for 2X660 MW THDC Khurja project
Site
Khurja, Uttar Pradesh
Client
L and T - MHI POWER BOILERS PRIVATE LIMITED
Customer
M/s. THDC India Ltd.
Project Duration
32 months
Our Scope of Work
Mechanical Erection works of Unit #1, 660MW Boiler & its Auxiliaries |
Date of Completion
Ongoing