ERECTION OF CEILING GIRDER NEYVELI NEW TPP


EDAC has successfully Completed the erection activities of Unit-1 of 2 X 500 MW Boiler Ceiling Girders ( 7 nos & 831 MT), Completed this major milestone activity in just 14 days time. ie From 29.11.2016 to 12.12.2016. NEW NEYVELI THERMAL POWER PLANT