2X 300 MW JSW THERMAL POWER PROJECT

Name of work : Erection of Boiler, ESP & its Auxiliaries and LSTK of BoP for 2X300 MW Thermal Power Project.
Site :

Toranagallu, Karnataka.

Client :

M/s. JSW, Karnataka.

Customer :

M/s. JSW, Karnataka

Consultant   M/s. TCE, Bangalore.
Project Duration :

22 Months

Our Scope of Work : Lump Sum Turnkey basis Balance of Plant works.
  • Coal Handling Plant
  • Ash Handling Plant
  • Cooling Water System
  • HVAC System
  • Air Compressor System
  • Fire Fighting System
Lump Sum Turnkey basis Electrical, Control & Instrumentation works for BTG & BoP.

Erection of Boiler, ESP & its Auxiliaries.

Date of Completion

: October 2008  

3 x 100 TPH BOILER NIRMA COUSTIC SODA PLANT

Name of work : Mechanical Erection works for 3X100 TPH Boiler
Nirma Coustic Soda Plant.
Site :

Bhavnagar, Gujarat.

Client :

M/s. Lentjes Energy Technik, Germany.

Customer :

M/s. Nirma Industries, Gujarat.

Consultant   M/s. Lentjes Energy Technik, Germany.
Project Duration :

19 Months.

Our Scope of Work : Erection of Non Pressure Parts, Air Pre-Heaters, ESP, Structure, Platform & Galleries, Backstays, Lignite Bunkers, Lime Stone Bunkers.

Date of Completion

: March 2000

20 MW RAJASHREE CEMENTS CAPTIVE POWER PROJECT.

Name of work : Mechanical Erection works for 20 MW Captive
Thermal Power Project
Site :

Malkhed, Karnataka.

Client :

M/s. Rajashree Cements, Malkhed, Karnataka.

Customer :

M/s. Rajashree Cements, Malkhed, Karnataka.

Consultant   M/s. TCE, Bangalore.
Project Duration :

18 Months.

Our Scope of Work : Erection of Boiler, TG Set, Supports and LP Piping.

Date of Completion

: June 1996

6 MW BIO METHANISATION ASIAN BIO ENERGY POWER PROJECT

Name of work : Engineering, Procurement & Electro Mechanical Erection works for 6 MW Bio Methanisation Power Project.
Site :

Lucknow, U.P.

Client :

M/s. Jeevitha Engineering Pvt.Ltd., Chennai.

Customer :

M/s. Asian Bio-Energy Ltd.

Project Duration :

8 Months.

Our Scope of Work : Engineering, Procurement & Construction of Piping, Conveyors& Structure. Installation of Electrical Cabling and Cable Tray.

Date of Completion

: December 2003

ITC PRIMARY MANUFACTURING PLANT PROJECT

Name of work : EPC Works for ITC's Primary Manufacturing Division (PMD) in Bangalore.
Site :

Bangalore.

Client :

M/s. Bovis Land Lease, Bangalore.

Customer :

M/s. ITC, Bangalore.

Consultant :

M/s. Bovis Land Lease, Bangalore.

Project Duration :

24 months.

Our Scope of Work : Erection of Steam & Condensate Piping.

Date of Completion

: April 2002

CHEMPLAST KARAIKAL CAUSTIC EXPANSION PROJECT

Name of work : Design, Supply, Fabrication and Erection of EDC Storage Tank
for Chemplast Sanmar, Karaikal.
Site :

Karaikal, TN.

Client :

M/s. Chemplast Sanmar Limited, Chennai

Customer :

M/s. Chemplast Sanmar Limited, Chennai

Consultant : M/s. Technip, Chennai.
Project Duration :

7 months.

Our Scope of Work : Design, Supply, Fabrication & Erection of EDC Storage Tanks. (20,000 Cu.M, 45 M Dia and 14.5 M Ht.)

Date of Completion

: January 2004.

 

 
 